PROJECT AUTHORIZATION | PACKET ID: PMT-YDL4 |
CONTRACT ID | EMARS PROGRAM CODE | AUTHORIZATION NO: | |
1377701D | 13777 | 4 | |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID | PROJECT ID NUMBER | FEDERAL PROJECT NUMBER | 6 YR PLAN ITEM NUMBER | 6 YR PLAN ITEM PARENT NUMBER |
056 006 5 131-136 |
NHPP 0656088 |
05-20061 | 99-00369.1- |
PROJECT TYPE | PROJECT LENGTH | NUMBER OF BRIDGES | SYSTEMS |
BRIDGE REPLACEMENT | 4.4320 MI |
PROJECT PHASE & RESPONSIBILITY |
PLANNING | DESIGN | RIGHT OF WAY | UTILITIES |
CONSTRUCTION | TITLE DEEDED TO: | MAINTENANCE | OTHER | |
FUNDING & TIME ACCOUNTABILITY |
PARTICIPATING AGENCIES | |||||||
FEDERAL | FHWA | STATE | KYTC | LOCAL | OTHER |
ITEM NUMBER | PHASE | FUND | PROGRAM | FEDERAL FISCAL YEAR | STATE FISCAL YEAR |
||
FEDERAL APPR CODE |
CURRENT FUNDING REQUEST | ||||||
5-20061 | D | 1200 | FD52 | 2024 | 2024 | Y001 | $1,350,000.00 |
5-20061 | D | 1100 | FD52 | 2024 | 2024 | $150,000.00 | |
CURRENT FUNDING REQUEST TOTAL: $1,500,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE | TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING | $0.00 |
DESIGN | $10,950,000.00 |
UTILITIES | $0.00 |
R/W | $0.00 |
CONSTRUCTION | $0.00 |
NON-HIGHWAYS | $0.00 |
Total: $10,950,000.00 |
REMARKS: | THIS AUTHORIZATION PROVIDES $400,000 OF ADDITIONAL DESIGN FUNDS FOR CEI SERVICES DURING THE PRECONSTRUCTION PHASE OF THE CMGC CONTRACT, AND $1,100,000 OF ADDITIONAL DESIGN FUNDS FOR GEOTECHNICAL WORK. |
Project Approval Recommended By: James Ballinger 3/15/2024 |
Signed and Approved by: Jim Gray 3/15/2024 |
AUTHORIZATION LOCATION | ||||||
ITEM NO. | COUNTY | DIST | FACILITY NAME |
ROUTE | LENGTH | SCOPE |
05-20061.00 | JEFFERSON
|
5 | I-65 | 4.4320 MI | ADDRESS PAVEMENT NEEDS ON I-65 BETWEEN MP 131.24 AND MP 135.672 AND TO REPLACE BRIDGE OVER HILL STREET AT MP 133.873; REPLACE BRIDGE OVER BROOK STREET AT MP 134.753, AND TO REPLACE BRIDGE OVER JACOB AND BROADWAY AT MP 135.273. |